How should a project manager interpret an 8-point run in a process with 1 point located out of control limit?
A、It is a normal situation, nothing should be done.
B、Control limits should be widened.
C、It is an abnormal situation; production processes should be corrected.
D、It is a warning signal; quality measurement systems should be updated.