信息系统项目管理师-pmp练习题-1
信管考点分类:英语
试题来源:信息系统项目管理师-pmp练习题-1

试题内容

You are having difficulty estimating the cost of a project. Which of the following best describes the most probable cause of your difficulty ?
A. Inadequate scope definition.
B. Unavailability of records from previous projects.
C. Lack of historical records from previous project.
D. Lack of company processes.