第65题
The( )provides the project manager with the authority to apply organizational resources to project activities.
A.project management plan
B .contract
C.project human resource plan
D .project charter
第66题
Estimating activity durations uses information on activity scope of ( ), required resource types, estimated resource quantities, and resource calendars.
A. milestone
B. baseline
C. quality
D. work