Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )
A、fast tracking
B、what-if scenario analysis
C、resource leveling
D、critical chain method