In the project management context,  (  ) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial  to  project  completion,  successfully  meeting  customer  and  other stakeholder requirements, and managing expectations.
A.integration
B.scope
C.process
D.charter