2017年信息系统项目管理师最新英语模拟题(2)
信管考点分类:未指定
试题来源:2017年信息系统项目管理师最新英语模拟题(2)

试题内容

During the execution phase, the supplier selection team gathers evaluation materials to make a selection decision for a customer relationship management system.For this work, the project manager will use which of the following?
A、Proposal evaluation sheet
B、Make-or-buy analysis
C、Procurement statement of work
D、Earned value analysis