An installation project of water treatment equipment uses advanced technology. The project team with penalty clauses has detailed work instructions expertise. Which types of contracts should the project manager used?
A、Fixed-price Contracts (FP)
B、Cost Plus Fixed Fee Contracts (CPFF)
C、Cost Plus Incentive Fee Contracts (CPIF)
D、Time and Material Contracts (T&M)