试题内容
查看答案
An installation project of water treatment equipment uses advanced technology. The project team with penalty clauses has detailed work instructions expertise. Which types of contracts should the project manager used?
A、Fixed-price Contracts (FP)
B、Cost Plus Fixed Fee Contracts (CPFF)
C、Cost Plus Incentive Fee Contracts (CPIF)
D、Time and Material Contracts (T&M)
查看答案
你可能感兴趣的试题