第64题
在质量控制过程中,经常会使用一些工具和方法。(1)是一种基于80/20原理,用于找出影响项目产品或服务质量的主要因素的方法。(2)不属于质量控制活动。
(1)A.流程图
B.帕累托图
C.控制图
D.鱼骨图
(2)A.产品测试
B.抽样
C.对不合格进行原因分析
D.过程分析
第75题
In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method,precedence relationships between acticities are represented by cireles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.
A、causality diagram
B、Gantt chart
C、histogram
D、arrow diagram
答案解析与讨论:https://www.ruantiku.com/shiti/3952210979.html
In a project plan, when the project manager schedules activities, he (or she) often uses ( ) method,precedence relationships between acticities are represented by cireles connected by one or more arrows. The length of the arrow represents the duration of the relevant activity.
A、causality diagram
B、Gantt chart
C、histogram
D、arrow diagram
答案解析与讨论:https://www.ruantiku.com/shiti/3952210979.html